17th Ave SW | Construction Schedule, 2018

Stay in the know with what’s happening and where down 17th Ave S.W.
Sidewalks are open, so no matter how you travel to the avenue, you’ll always be able to visit your favourite
stores. There is ample parking on 17th Ave S.W. and in the area.

College Lane* – 7th Street

  • – Work Starting Week Commencing –  September 2nd, 18
  • – Work Finishing Week Commencing –  September 16th, 18
  • – Duration – 2 weeks

What’s involved:

The work includes replacing utilities between College Lane and 7th Street (including 7 St. S.W. intersection), as well as road construction.

*College Lane to remain open at all times

7TH STREET INTERSECTION

  • – Work Starting Week Commencing –  September 9th, 18
  • – Work Finishing Week Commencing –  September 16th, 18
  • – Duration – 2 weeks

What’s involved:

The work includes replacing utilities across the 7th street intersection, as well as road construction.

7TH – 8TH STREET

  • – Work Starting Week Commencing – September 2nd, 18
  • – Work Finishing Week Commencing – October 14th, 18
  • – Duration – 7 weeks

What’s involved:

The work includes replacing utilities along 17th Ave from 7th Street up to 8th Street, as well as road construction.

8TH STREET INTERSECTION

  • – Work Starting Week Commencing – September 23rd, 18
  • – Work Finishing Week Commencing – October 3rd, 18
  • – Duration – 2 weeks

What’s involved:

The work includes replacing utilities across the 8th street intersection, as well as road construction.

8TH – 9TH* STREET

  • – Work Starting Week Commencing – September 23rd, 18
  • – Work Finishing Week Commencing – November 4th, 18
  • – Duration – 7 weeks

What’s involved:

The work includes replacing utilities along 17th Ave from 8th Street up to 9th Street, as well as road construction.

*9th Street to remain open at all times

After thirty years, we’re reconstructing 17 Avenue S.W. and our plans are going to make it awesome for all of us, for decades to come. The overall construction will be between Macleod Trail S.E. and 14 Street S.W. to improve sidewalks, road design, and underground utilities.

17th Ave is one of Calgary’s most vibrant neighbourhoods to shop, eat, visit and do business.

If you have questions about the project or would like to receive project updates, feel free to email the project team.

The City of Calgary

 

Business owners and residents can stay updated on the latest construction update.